In March 1940, on the bank of the Muthirapuzha below Munnar, the Travancore Diwan C. P. Ramaswamy Iyer started the first generating unit at Pallivasal, and Kerala had hydroelectric power for the first time. The Pallivasal Hydro Electric Project was built in the reign of Sree Chithira Thirunal Balarama Varma, and the township that grew up round the station still carries his name, Chithirapuram. Just 836 metres down the same bank, the river breaks over rock at a spot everyone now calls Power House Waterfalls, named after the machine above it.

That first machine was soon joined by others, because once the power was flowing Travancore wanted more of it. A second unit came on in February 1941 and a third in February 1942, all three Pelton wheels made by Escher Wyss of Switzerland. In 1950 each was uprated from four and a half megawatts to five. A Pelton wheel is the turbine for a modest amount of water falling a very long way. That is exactly what the High Range offers and what the flat country downstream does not.

Turbines like that need a steady supply, so in 1944 a masonry weir was finished across the Muthirapuzha upstream. It stands 10.9 metres high and 39.6 metres long, with three spillway gates. Its job is not to store water but to lift the river out of its bed and send it through a conducting system to the power house on the right bank. The weir sits just below Blossom Hydel Park, which is why the river beside the flower walks there is wide and still.

A second phase then went further up the hills so that the water would never run short. It added three more Pelton sets of seven and a half megawatts from Boving of the United Kingdom. It also built the Kundala and Mattupetty dams upstream to store the monsoon water. That took Pallivasal to 37.5 megawatts and roughly 284 million units a year. It also means the lakes where day-trippers pedal boats above Munnar are part of the same plumbing.

The same water keeps working after it leaves Pallivasal. The Muthirapuzha is a tributary of the Periyar. Below the station it runs on to the Sengulam and Panniyar power houses, so one flow turns three sets of machines before it reaches the plains. It is among the oldest cascades of its kind in India. It also explains why a district with almost no industry has three power houses within fifteen kilometres of each other.

The chain was meant to have one more link, and its shell still stands. The Pallivasal Extension Scheme was planned as two 30-megawatt units making 153.9 million units a year. A tunnel of about three and a half kilometres and a penstock of 1,285 metres would feed a new power house at Chithirapuram, and the water would run on by gravity into the Sengulam reservoir. KSEB gave it revised sanction on 20 November 2001 for ₹269.87 crore. The work went to the ESSAR–DEC–CPPL consortium, but on 13 September 2018 the board ended the contract for poor progress at site.

That unfinished building stands 1,065 metres from the waterfall, and it is the one many visitors photograph as "the power house", although it has never generated anything. The old station that did the work since 1940 is the quieter building further up the bank. Together they make the valley at Chithirapuram an open-air history of how Kerala learned to turn its mountains into light.

People who come down from Munnar to see that history usually end at the river itself, where the water returns from the turbines and spreads over the rocks. What they find there depends on the station as much as the weather. The river below Pallivasal runs on demand, and that is the story of Power House Waterfalls and its regulated river.

Frequently asked questions

When did Pallivasal start generating power?

The first unit was started in March 1940 by Travancore Diwan C. P. Ramaswamy Iyer. It was the first hydroelectric power in Kerala.

How big is the Pallivasal power station?

It has three 5 MW and three 7.5 MW Pelton sets. That is 37.5 MW, about 284 million units a year.

What is the Pallivasal Extension Scheme?

It is a planned 2 × 30 MW power house at Chithirapuram. KSEB sanctioned it in 2001 and ended the contract in September 2018 for poor progress.

Why is the waterfall called Power House Waterfalls?

It is named after the Pallivasal power house, which stands 836 metres up the same bank of the Muthirapuzha.