On 17 May 2026, K Vijayan and his family carried their things into house No. 38 in the D cluster at Elstone Estate, Kalpetta. They were the first family to move into the Wayanad township. Vijayan had lost his home at Chooralmala in the landslide of 30 July 2024. "I never imagined that I would one day own such a beautiful house," he told Onmanorama that day.
His new house stands on land that was a tea estate until the disaster changed its use. The landslide that hit Mundakkai and Chooralmala killed 298 people, including 32 who were declared dead after being listed as missing. More than 630 people were rescued. Whole villages could not be rebuilt where they had stood. So the state looked for safe, open ground close to the district headquarters.
It found that ground at Elstone Estate near the Kalpetta bypass. On 11 April 2025 the government paid Rs 44.33 crore into court to take over the land, as Onmanorama reported. The estate covers about 64.4 hectares. The plan was for 410 houses, and about 1,662 people are expected to live in the township.
Each of those houses follows one design, so every family starts from the same footing. The homes are single-storey, 1,000 sq ft, on foundations strong enough for a second floor later. Each has a master bedroom, two more rooms, a sit-out, a living area and a study. A dining hall, a kitchen and storage complete the plan. Every family receives the title deed for seven cents of land.
The first phase was meant to open in February 2026, but the building work was not ready in time. The handover moved to 1 March. That day Chief Minister Pinarayi Vijayan inaugurated the first phase and handed keys and title deeds to 178 families. Finishing work and the Assembly election code then kept many houses empty for weeks.
That is why Vijayan's move in May mattered so much to the families still waiting. By then the lead contractor, the Uralungal Labour Contract Cooperative Society, had completed quality checks on 150 of the first 178 houses. Other families followed, and by September 2026, 177 of the 178 houses were occupied. One stayed empty because of a dispute over its claim.
The second phase brought its own frustrations. In September 2026 second-phase families gathered at the site with placards, asking for faster work. Many of them were still living in rented homes. They asked for their rent support to continue until they moved in. Heavy rain had slowed painting and road laying, and the government said it reviewed progress every week.
Agriculture Minister T. Siddique gave the new targets at the site. He said all the houses should be finished by the end of October 2026, and roads and other main facilities by December. The plan is for a full settlement, not only houses. It includes a health centre, an anganwadi, a public market, community centres, playgrounds and a multipurpose centre with a library and a memorial.
For a visitor, the township is a neighbourhood where people are rebuilding their lives, so it is not a sight to tour. Chooralmala and Mundakkai are places of grief, and the families there ask for respect, not cameras. What helps Wayanad most is ordinary travel. Visitors stay in Kalpetta, eat in local restaurants and hire local guides, so their money reaches households across the district.
That ordinary travel is easy to plan from Kalpetta, which sits at the centre of the district. The coffee farms around the town are one way in, and the Wayanad coffee story explains how the crop shaped these hills. The Puliyarmala story tells of a Jain temple a few kilometres away.
The rain that brought the hillside down is also part of Wayanad's beauty, and the story of Lakkidi's rain explains where the monsoon falls hardest. The Meppadi and Chembra guide covers the hills nearest the affected villages. Beyond them lies the rest of Wayanad.
Frequently asked questions
Where is the Wayanad township?
At Elstone Estate near the Kalpetta bypass, on about 64.4 hectares of former tea estate.
Who is it for?
Families who lost their homes in the 30 July 2024 landslide at Mundakkai and Chooralmala.
How many houses are planned?
410 houses. The first 178 were handed over on 1 March 2026, and the rest were due by the end of October 2026.
How big is each house?
Each house is 1,000 sq ft on seven cents of land, with foundations for a second floor.